What does the term 'scope creep' refer to?

Prepare for the Landini Certified Associate in Project Management (CAPM) Test. Review flashcards, tackle multiple choice questions, and gain insights with hints and explanations. Ensure you're ready for your examination success!

Multiple Choice

What does the term 'scope creep' refer to?

Explanation:
Scope creep happens when the amount of work in a project grows beyond what was originally agreed, and it does so in an uncontrolled way because changes aren’t entering through a formal change-control process. In practice, new requirements, features, or tasks get added after the baseline is set, and those additions aren’t properly analyzed for impact on time, cost, and resources. The result is the project gradually expands, often delaying delivery, increasing costs, and degrading quality. To prevent scope creep, a clear change-control process is essential: any proposed change to scope should be documented as a change request, evaluated for its effects on schedule and budget, and only approved by the appropriate stakeholders before the scope is updated. For example, if a sponsor asks for a new feature mid-project, that request should go through change control, with impact analysis and budget adjustment if approved. Other options don’t fit because they describe things unrelated to expanding what you must deliver. Unplanned early completion isn’t about adding work; a formal process to approve budget increases is about budgeting governance, not expanding scope; and documenting stakeholder requirements is part of defining the project, not the creeping growth of work once the project is underway.

Scope creep happens when the amount of work in a project grows beyond what was originally agreed, and it does so in an uncontrolled way because changes aren’t entering through a formal change-control process. In practice, new requirements, features, or tasks get added after the baseline is set, and those additions aren’t properly analyzed for impact on time, cost, and resources. The result is the project gradually expands, often delaying delivery, increasing costs, and degrading quality.

To prevent scope creep, a clear change-control process is essential: any proposed change to scope should be documented as a change request, evaluated for its effects on schedule and budget, and only approved by the appropriate stakeholders before the scope is updated. For example, if a sponsor asks for a new feature mid-project, that request should go through change control, with impact analysis and budget adjustment if approved.

Other options don’t fit because they describe things unrelated to expanding what you must deliver. Unplanned early completion isn’t about adding work; a formal process to approve budget increases is about budgeting governance, not expanding scope; and documenting stakeholder requirements is part of defining the project, not the creeping growth of work once the project is underway.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy