If the diagonal trend line on a Burndown Chart runs above the plan line, what does this indicate?

More work remains than forecasted

On a burndown chart, you’re watching how much work remains as time progresses. The plan (ideal) line shows the expected pace to finish all work by the sprint’s end. If the actual trend line sits above that plan line, it means there is more work left than forecasted at that point, so progress is slower than planned. In other words, the project is behind schedule relative to the forecast. Costs aren’t directly shown by this chart, and being ahead of schedule would put the actual line below the plan line, while completing more work than forecasted would pull the line below the plan line as well.

The project is ahead of schedule

Costs are under control

More work is being completed than forecasted

Next Question
Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy