In earned value management, which metric indicates the difference between earned value and planned value?

Prepare for the Landini Certified Associate in Project Management (CAPM) Test. Review flashcards, tackle multiple choice questions, and gain insights with hints and explanations. Ensure you're ready for your examination success!

Multiple Choice

In earned value management, which metric indicates the difference between earned value and planned value?

Explanation:
Schedule Variance measures the difference between earned value and planned value. It is calculated by subtracting planned value from earned value, so EV minus PV. A positive result means you’re ahead of schedule, a negative result means you’re behind, and zero means you’re on track schedule-wise. The other metrics use different comparisons: Cost Variance looks at earned value versus actual cost, while the performance indices are ratios (EV/PV or EV/AC) that describe efficiency rather than the direct difference. So the metric that shows the gap between what was planned to be earned and what has actually been earned is Schedule Variance.

Schedule Variance measures the difference between earned value and planned value. It is calculated by subtracting planned value from earned value, so EV minus PV. A positive result means you’re ahead of schedule, a negative result means you’re behind, and zero means you’re on track schedule-wise. The other metrics use different comparisons: Cost Variance looks at earned value versus actual cost, while the performance indices are ratios (EV/PV or EV/AC) that describe efficiency rather than the direct difference. So the metric that shows the gap between what was planned to be earned and what has actually been earned is Schedule Variance.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy